Beaver Natural Gas Generating Plant
Hydro-Excavating for all new medium voltage conduits and cabling in operational combine cycle gas fired power plant in Clatskanie ,Oregon. Approximately. 27,650 feet of schedule 80 PVC underground, 83,500 feet of medium voltage cable from 1/0 to 750MCM, and over 200 medium voltage terminations. Installation of new owner furnished medium voltage switchgear in 2 shipping splits switching over redundant systems one at time to maintain plant operations and generation. Replacement of 15 medium voltage PCB filled supply transformers (the last PCB oil filled transformers in the entire PGE system) with OFCI new xmers.
Location: Clatskanie, OR